According to PRINCE2, which statement about the Configuration Management Strategy for the Outsourcing project is correct?

  1. Every project needs a Configuration Management Strategy, even if the organization has existing configuration management standards, because every project has different circumstances.
  2. A separate Configuration Management Strategy will be required for each of the suppliers within this project because each will have a different way of managing and storing products.
  3. A Configuration Management Strategy is unnecessary for this project because the MFH document control process is documented. It is acceptable simply to reference this in the Quality Management Strategy.

Answer(s): A



View Related Case Study

According to PRINCE2, which statement about appointing the MFH Quality Manager to administer the configuration management procedure is correct?

  1. The MFH Quality Manager should administer the configuration management procedure on this project because this task should always be assigned to corporate or programme management.
  2. The MFH Quality Manager should only administer the configuration management procedure on one project at a time. If the MFH Quality Manager already performs this task on another project, another individual should be appointed.
  3. The MFH Quality Manager would be suitable to perform this task because he is the author of the document control process and is likely to have the knowledge required for this role.

Answer(s): C



View Related Case Study

Having created the Issue Report and analyzed the impact of removing the Facilities Division from the scope of the Outsourcing project, the proposed option exceeds tolerance. \Nhat is the next action the Project Manager should consider?

  1. Create an Exception Report to inform the Project Board of the situation and the available options.
  2. Update the associated Configuration Item Records with details of the Issue Report that caused the change.
  3. Amend the Stage Plan for stage 3: remove all products related to the Facilities Division and add the activities required to deliver the new Government initiative.
  4. Create an Exception Plan to change all of the project's products to reflect the exclusion of services provided by the Facilities Division.

Answer(s): A



View Related Case Study

What products will be impacted by this change?

  1. All of the project's products created so far.
  2. Only those products created in the first three weeks of stage 3.
  3. All of the project's products which relate to or include services provided by the Facilities Division.
  4. No products would need to be changed but some will need to be removed from the project.

Answer(s): D