Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?

  1. Checkpoint Report
  2. End Stage Report
  3. End Project Report
  4. Product Status Account

Answer(s): B



Which is a purpose of a Project Product Description?

  1. Form part of the Work Package for the project product
  2. Provide the initial project budget to be refined in the Business Case
  3. Document the project mandate and gain approval for the project from the Project Board
  4. Define the quality required of the project's product

Answer(s): D



What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

  1. Directing a Project
  2. Controlling a Stage
  3. Managing a Stage Boundary
  4. Managing Product Delivery

Answer(s): B



Which statement about the Directing a Project process is FALSE?

  1. Supports the PRINCE2 principle of manage by exception
  2. Is triggered by a request to initiate a project
  3. Covers the day-to-day activities of the Project Manager
  4. Provides a mechanism for the Project Board to assure that there is continued business justification

Answer(s): C