Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

  1. Controlling a Stage
  2. Closing a Project
  3. Directing a Project
  4. Managing a Stage Boundary

Answer(s): D



Identify the missing words in the following sentence: During the Initiating a Project process the [?] before a project is authorized.

  1. minimum necessary is done to decide if a project is worthwhile
  2. aim is to establish sound foundations to achieve a successful project
  3. Project Brief is assembled and approved
  4. project approach appropriate for delivering a project is selected

Answer(s): B



Which of the following is NOT a purpose of the Closing a Project process?

  1. Plan the activities required to close a project
  2. Enable a comparison of the original objectives of a project against what was actually achieved
  3. Enable premature closure if the Project Board request that a project should no longer continue
  4. Provide a fixed point at which acceptance for the project product is confirmed

Answer(s): A



Which is NOT a purpose of the Organization theme?

  1. Define a project management team structure
  2. Define the level of tolerance for each level of the project management team
  3. Define the Project Board's responsibility for directing the project
  4. Define which role is accountable for the project's success

Answer(s): B