Which is a purpose of the Plans theme?

  1. Identify, assess and control any potential changes to the baseline
  2. Establish the project's structure of accountability
  3. Assess and control uncertainty
  4. Understand whether the targets are achievable

Answer(s): D



Which of the following is NOT an event-driven control?

  1. Project mandate
  2. Checkpoint Report
  3. Exception Report
  4. End of a stage

Answer(s): B



Which is a responsibility of a risk owner?

  1. Identify risks to the project that might occur in their department
  2. Own and authorize the use of the risk budget to fund risk responses
  3. Manage, monitor and control all aspects of an assigned risk
  4. Determine project risk appetite

Answer(s): C



Which is a type of issue?

  1. An expected dis-benefit
  2. An off-specification
  3. A project outcome
  4. A scope tolerance

Answer(s): B