Which is a difference between management and technical stages?

  1. Management stages require planning and technical stages do not
  2. Technical stages can overlap and management stages cannot
  3. Management stages deliver products and technical stages do not
  4. Technical stages require resources and management stages do not

Answer(s): B



Which describes the 'Identify Risks' step within the recommended risk management procedure?

  1. Identify responses to risks documented in the Business Case
  2. Gather information about the project environment and objectives
  3. Identify the roles to be involved in risk management activities
  4. Identify uncertainties that may impact on the delivery of the project objectives

Answer(s): D



Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?

  1. Business Case
  2. Plans
  3. Progress
  4. Quality

Answer(s): C



Which provides a single source of reference that may be used by people joining a project after it has been initiated so they can quickly and easily find out how the project is being managed?

  1. Project Brief
  2. Project Initiation Documentation
  3. Project mandate
  4. Project Product Description

Answer(s): B