Which regular report provides the Project Board with a summary of stage status?

  1. Communication Management Strategy
  2. Project Brief
  3. Highlight Report
  4. Checkpoint Report

Answer(s): C



Which statement describes the Implement' step within the recommended risk management procedure?

  1. Take planned action to respond to a risk
  2. Implement the responsibilities for risks defined in the Risk Management Strategy
  3. Assess the proximity of a risk
  4. Identify the level of risks that can be tolerated by the project

Answer(s): A



Upon what environment is PRINCE2 based?

  1. Operational
  2. Configuration
  3. Programme
  4. Customer/supplier

Answer(s): D



What process is used by the Project Board to respond to an Exception Report?

  1. Controlling a Stage
  2. Managing a Stage Boundary
  3. Managing Product Delivery
  4. Directing a Project

Answer(s): D