Which is a purpose of the Managing Product Delivery process?

  1. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
  2. Provide a controlled link between the Project Manager and the Team Manager(s)
  3. Enable the Project Board to request updates to the current Team Plan
  4. Establish solid foundations for the project

Answer(s): B



Which statement describes the responsibilities of a risk actionee?

  1. Identifying risks to the project that might occur in their department
  2. Owning and authorizing the use of the risk budget to fund risk responses
  3. Managing, monitoring and controlling of all aspects of an assigned risk
  4. Carrying out a risk response action to respond to a particular risk

Answer(s): D



Which is a benefit of using PRINCE2?

  1. Is a method specifically designed for technical projects
  2. Provides for the efficient and economic use of management time
  3. Includes many of the proven planning techniques, such as critical path analysis
  4. Can be used to manage both projects and programmes

Answer(s): B



Which is a task of product-based planning?

  1. Design the plan
  2. Create the product flow diagram
  3. Analyze the risks
  4. Prepare the schedule

Answer(s): B