Which is a purpose of a Risk Register?

  1. Capture risks that may occur during the project
  2. Record how risk management activities will be undertaken on the project
  3. Record the risk tolerance for the project
  4. Capture issues which are impacting on the delivery of the project objectives

Answer(s): A



What product forms the contract' between the Project Board and the Project Manager?

  1. Project Brief
  2. Project Initiation Documentation
  3. Project mandate
  4. Project Plan

Answer(s): B



Which activity takes place within the Managing a Stage Boundary process?

  1. Produce Highlight Reports
  2. Take corrective action within the limits of a stage's tolerance
  3. Produce an Exception Plan
  4. Authorize a Stage Plan for the next stage

Answer(s): C



Which is created during the Starting up a Project process?

  1. Project mandate
  2. Project management team role descriptions
  3. Communication Management Strategy
  4. Quality Register

Answer(s): B



Which is a purpose of a Configuration Management Strategy?

  1. Provide a record of each configuration item and any important relationships between them
  2. Define how the products and their versions will be identified
  3. Define whether a project will use a risk budget
  4. Identify who will set up the Quality Register

Answer(s): B