Free PRINCE2-Re-Registration Exam Braindumps (page: 24)

Page 23 of 62

Which role is responsible for the management of a risk assigned to it?

  1. Project Support
  2. Risk owner
  3. Risk actionee
  4. Project Assurance

Answer(s): B



What is the definition of a project outcome?

  1. A measurable improvement that is perceived as an advantage by one or more stakeholders
  2. The reason for the project
  3. The result of the change derived from using the project's outputs
  4. The project's specialist products.

Answer(s): C



What is defined as a temporary organization that is created for the purpose of delivering one or more business products?

  1. Corporate or programme management
  2. A project
  3. A product breakdown structure
  4. A user group

Answer(s): B



Why is the Initiating a Project process used?

  1. To decide which project approach is suitable for the project
  2. To fully understand how the project objectives will be achieved before committing significant resources
  3. To produce the required Work Packages
  4. To enable corporate or programme management to give authorization to deliver a project

Answer(s): B






Post your Comments and Discuss PRINCE2 PRINCE2-Re-Registration exam with other Community members: