Which process provides the Project Board with the information it requires in order to commit resources to the project?

  1. Managing Product Delivery
  2. Initiating a Project
  3. Controlling a Stage
  4. Directing a Project

Answer(s): B



Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?

  1. Principles
  2. Processes
  3. Tailoring PRINCE2 to the project environment
  4. Themes

Answer(s): A



Which should be funded by a change budget?

  1. Increase in agreed scope
  2. Initiation stage
  3. Change Authority
  4. Handover activities

Answer(s): A



Which of the following describes a use of a Configuration Item Record?

  1. Define the identification scheme to be applied to the project
  2. Identify the techniques and procedures required within the Work Package
  3. Record the change in a product's status
  4. Record the reporting requirements for the Work Package

Answer(s): C