Which of the following is a primary objective of risk exposure analysis?

  1. Collecting information that can be used for future risk analysis
  2. Defining risk aversion steps
  3. Estimating the impact of the risk on the project and the product
  4. Assessing whether the identified risks should be accepted or mitigated

Answer(s): C



Software trouble reports should be analyzed by a developer or a maintainer to determine

  1. whether the software errors are distinguishable and reproducible
  2. whether the maximum number of allowable errors and anomalies has been reached
  3. the problem effect and the fix rate
  4. what regression testing is required and when

Answer(s): A



Rank order, from first to last, the following elements to be developed when a software engineer is translating customer expectations.

1. Actual results
2. Design specifications
3. Code
4. Functional specifications

  1. 2, 3, 4, 1
  2. 3, 4, 1, 2
  3. 4, 2, 3, 1
  4. 4, 3, 2, 1

Answer(s): C



Which of the following is most likely to compromise the integrity of data collected in a software metrics program?

  1. Using automated data collection tools
  2. Using nonparametric statistical methods
  3. Using the data to monitor team performance
  4. Using the data to monitor individual performance

Answer(s): D



Which of the following is likely to contribute most to an effective project meeting?

  1. Distributing and following an agenda
  2. Assigning action items during the meeting
  3. Limiting interruptions
  4. Recording minutes during the meeting

Answer(s): A