Free CSQE Exam Braindumps (page: 3)

Page 2 of 23

Informal change control is appropriate only

  1. before software configuration items become part of a baseline
  2. until the production baseline is built
  3. when a project has a short duration and limited functionality
  4. until acceptance testing begins

Answer(s): A



The publisher of a social services resource guide has contracted for the development of an electronic version of its guide. The product has been loosely defined to date due to the limited knowledge of the technology available to the user community and to the limited technical expertise of the publisher's staff. The development team for this project will consist of two employees who are new to the company and one programmer with minimal experience.
Which of the following approaches would best serve the needs of this project?

  1. Cleanroom methods
  2. Waterfall model
  3. Object oriented development
  4. Iterative development

Answer(s): D



Software process evaluations are used to determine

  1. how much progress the supplier is making toward completing assigned tasks
  2. how much progress the supplier is making toward process improvement
  3. potential risks to the assigned projects
  4. whether a project is ready to make the transition to the next phase

Answer(s): C



Which of the following statements is true about white-box testing?

  1. It includes functional testing.
  2. It includes loop testing.
  3. It is usually done after black-box testing.
  4. It is usually done during the integration testing phase.

Answer(s): B






Post your Comments and Discuss Quality Assurance CSQE exam with other Community members:

CSQE Discussions & Posts