Which of the following is the critical path in the activity network above?

  1. A, B, C, F, G, I, J
  2. A, B, D, E, F, G, I, J
  3. A, B, D, E, F, H, I, J
  4. A, K, L, M, J

Answer(s): D



A particular code unit has had four builds since version 1.0. Three of those builds were the result of design changes.
Which of the following version identifiers could describe the current build?

  1. 3.0
  2. 3.4
  3. 4.1
  4. 4.3

Answer(s): C



A software manager for a company that provides embedded, real-time software is asked to benchmark the department's development and test processes. It would be appropriate for the manager to select a process model from a company that develops software for

  1. data processing applications
  2. database management systems
  3. robotic systems
  4. graphical user interfaces

Answer(s): C



Which of the following models is characterized as being suitable for a software development project that has well-defined requirements?

  1. Prototyping
  2. Spiral
  3. Waterfall
  4. Iterative

Answer(s): C