A project that is in the implementation phase is six weeks behind schedule. The delivery date for the product is four months away. The project is not allowed to slip the delivery date or compromise on the quality standards established for this product.
Which of the following actions would bring this project back on schedule?

  1. Eliminate some of the requirements that have not yet been implemented.
  2. Add more engineers to the project to make up for lost work.
  3. Ask the current developers to work overtime until the lost work is recovered.
  4. Hire more software quality assurance personnel.

Answer(s): A



Change X requires a higher level of authority than Change Y in which of the following pairs?

  1. Option A
  2. Option B
  3. Option C
  4. Option D

Answer(s): D



Which of the following deals with legally binding promises made in exchange for appropriate consideration?

  1. Contracts
  2. Copyrights
  3. Patents
  4. Torts

Answer(s): A

Explanation:

Contracts are agreements that are legally binding. To be legally binding, the promises made in the contract must be exchanged for appropriate consideration. In other words, there has to be something of value received by both parties. If a legal contract is breached, the parties to the contract can seek legal remedies.


Reference:

The Certified Software Quality Engineering Handbook by Linda Westfall ­ page 12. CSQE Body of Knowledge Area: I.B.2



Which of the following documents would NOT be used as requirements against which an auditor would conduct an evaluation of compliance and/or conformance?

  1. A tailored process
  2. A coding standard
  3. A requirements specification
  4. A quality record

Answer(s): D

Explanation:

Audit evaluation criteria (requirements against which conformance and/or compliance is evaluated) provide the objective requirements and guidelines against which conformance and/or compliance is evaluated.
While quality records are used as objective evidence to evaluate compliance and/or conformance, they are never the requirements that an audit evaluation is performed against.


Reference:

The Certified Software Quality Engineering Handbook by Linda Westfall ­ pages 119-120. CSQE Body of Knowledge Area: II.C.3






Post your Comments and Discuss Quality Assurance CSQE exam with other Community members:

CSQE Discussions & Posts