The ASAP Focus Methodology defines a proposal framework as an accelerator to help you produce the proposal document during the evaluation phase.

Which document is part of the proposal framework?

  1. Sales presentations
  2. Marketing collateral
  3. Customer qualification questionnaire
  4. Solution scope document

Answer(s): D



In the SAP Business All-In-One implementation approach you focus on getting the people ready, rather than getting the system ready as we do in the traditional approach.

What does "getting people ready" encompass?

  1. Supporting the customer in conducting organizational change management by providing them with relevant material and accelerators that are available in ASAP Focus Roadmaps.
  2. Making sure that the people are motivated and competent to use the new system, change their work habits, and confident that the organization is committed to this project
  3. Training key users how to contribute to implementation, and training end users how to use the new business scenarios in their daily operations
  4. Ensuring that management is committed to making the employees allocated to the implementation project available and that the end users are adequately trained

Answer(s): B



SAP has created a special offering based on the SAP BusinessObjects Data Integrator, specifically designed for data migration to SAP Business All-in-One.

During an SAP implementation, there are 5 primary tasks associated with the process of data migration.

Which list of data migration process steps is in the correct sequence?

  1. Data Mapping, Data Extraction, Data Validation, Data Load, Data Reconciliation
  2. Data Extraction, Data Reconciliation, Data Validation, Data Mapping, Data Load,
  3. Data Extraction, Data Mapping, Data Validation, Data Load, Data Reconciliation
  4. Data Extraction, Data Load, Data Mapping, Data Validation, Data Reconciliation

Answer(s): C



You want to settle a hierarchy of internal orders to a cost center in a single settlement run.

What is the main criterion for the complete settlement?

  1. It is not possible to perform all the settlements in a single settlement run. Ensure that you perform as many settlement runs as the number of levels in the order hierarchy.
  2. The orders must be settled from the lowest to the highest hierarchy number.
  3. All the orders of the hierarchy must be settled to zero.
  4. A reference to all the internal orders must appear in the settlement document.

Answer(s): C



Your customer has a multi-company setup and sometimes sells products that belong to a different company code.

Which organizational entity is involved in the intercompany transaction?

  1. Plant
  2. Profit Center
  3. Cost Center
  4. Client

Answer(s): A