SAP C_ACTIVATE12 Exam
SAP Certified Associate - SAP Activate Project Manager Exam (Page 6 )

Updated On: 11-Jan-2026

Working in an Agile approach, what should your planning look like at the Beginning of the realize phase?

  1. User stories are in a ready state for NO more than the first three sprints
  2. Project scope and planning are completed and final
  3. Timelines of the sprint may differ due to the workload
  4. Go-live scope is fixed on the first of January the following year

Answer(s): A



The tasks associated with Landscape transportation are in which workstream? Please choose the correct answer.

  1. Transition to Operations
  2. System & data migration
  3. Application Solution Adoption
  4. Technical Architecture and Infrastructure

Answer(s): B



What must be defined in the Preset Phase of implementation to enable configuration of business processes?

  1. Organizational Structure
  2. Master Data
  3. Expert Configuration
  4. Chart of Accounts

Answer(s): A,D



Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase? There are 2 correct answers to this question.

  1. Kick-off workshop
  2. Integration prerequisites confirmation
  3. Fit-to-standard workshop
  4. Configuration definition

Answer(s): C,D



What is a strategy level 0(L0) artifact?

  1. Approach document that is developed by a united project team (partner+ customer)
  2. Optional information that is NOT important for project activities
  3. Project result that is developed solely by the partner
  4. Preliminary strategy developed by the customer to approach the project in a specific workstream

Answer(s): D



Viewing page 6 of 41
Viewing questions 21 - 24 out of 198 questions