Which of the following is true about a cloud implementation project? There are 2 correct answers to this question.

  1. The entire transport system is kept intact and up and running.
  2. Starter Systems are not required to be in place for the 'Fit to Standard' workshops.
  3. The Starter System is specific to SAP S/4HANA Cloud.
  4. In the prepare phase of a cloud implementation project the project team provide the customer with materials to review as self-enablement.

Answer(s): C,D



What are the two options for transferring data to SAP S/4HANA Cloud?

  1. Data Aging (1K8)
  2. Data Migration to SAP S/4HANA from Staging (2Q2)
  3. Data Migration to SAP S/4HANA from File (BH5)
  4. Data Migration to SAP S/4HANA from SAP (BH3)

Answer(s): B,C



What technique helps agile project teams to prioritize a large, flat backlog?

Please choose the correct answer.

Response:

  1. Fit/Gap Analysis
  2. User Story Mapping
  3. Retrospective
  4. Planning Poker

Answer(s): B



What configuration cannot be changed after Preset phase activation"

  1. New country activation
  2. Organizational structure keys
  3. Maintain Takeover Date for Asset Accounting
  4. Fiscal year variant

Answer(s): B,D



What APIs (Application Programming Interface) are used to connect SAP Cloud to SAP on premise solutions?

  1. BAPI
  2. SOAP
  3. IDoc
  4. Data

Answer(s): C