SAP C_ACTIVATE12 Exam Questions
SAP Certified Associate - SAP Activate Project Manager Exam (Page 7 )

Updated On: 21-Feb-2026

When is the Quality System upgraded to the latest release?

  1. Don the Release to Customer (RTC) date
  2. The second weekend after the RTC date
  3. The first weekend after the RTC date
  4. The third weekend after the RTC date

Answer(s): A



Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition?

There are 3 correct answers to this question.

Response:

  1. Operations impact analysis
  2. Custom code adjustment
  3. Delta configuration
  4. Development system migration
  5. Sandbox system migration

Answer(s): B,C,D



How do you achieve frequent checkpoints with the end user in an Agile delivery approach? There are 2 correct answers to this question.

  1. Demo the SAP model company
  2. User acceptance test
  3. Solution demo for sprints
  4. Solution review for waves

Answer(s): C,D



What are some characteristics of the Quality system?

  1. Used to run your business in SAP S/4HANA Cloud
  2. Used for quality assurance check of business processes during quarterly upgrades
  3. Decommissioned 30 days after Production system provisioning
  4. Configurable system during implementation

Answer(s): B,D



In the System conversion to SAP S/4 HANA Deploy phase, which of the following tasks are included? Please choose the correct answer.

  1. Scheduling project plan
  2. Final testing
  3. Interface setup
  4. Hyper care support

Answer(s): B