What are some of the key topics covered in the customer team enablement workshops? NOTE: There are 3 correct answers to this question.

  1. Technical expertise
  2. Project management
  3. Project sourcing approach
  4. Solution expertise
  5. Planning skills

Answer(s): A,B,D



When is the Quality System upgraded to the latest release?

  1. Don the Release to Customer (RTC) date
  2. The second weekend after the RTC date
  3. The first weekend after the RTC date
  4. The third weekend after the RTC date

Answer(s): A



Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition?

There are 3 correct answers to this question.

Response:

  1. Operations impact analysis
  2. Custom code adjustment
  3. Delta configuration
  4. Development system migration
  5. Sandbox system migration

Answer(s): B,C,D



How do you achieve frequent checkpoints with the end user in an Agile delivery approach? There are 2 correct answers to this question.

  1. Demo the SAP model company
  2. User acceptance test
  3. Solution demo for sprints
  4. Solution review for waves

Answer(s): C,D