What is the added value of a change plan?
Note: There are 2 correct answers to this question.

  1. It allows you to coordinate and monitor the progress of all change management activities.
  2. It facilitates the ranking of change management activities according to their importance.
  3. It provides important input for updating the overall project plan.
  4. It helps to identify required resources for the change management execution and to ensure their availability.

Answer(s): A,D

Explanation:

A change plan in SAP's Organizational Change Management framework is a structured tool that outlines the scope, activities, and timeline for managing the people side of a project, such as an SAP cloud implementation. Option A is correct because coordinating and monitoring progress is a core function of the change plan--it ensures that all change management activities (e.g., communication, training, stakeholder engagement) are executed in sync with the project timeline. Option D is also correct because identifying and securing resources (e.g., change agents, trainers, or tools) is critical for effective execution, and the change plan serves this purpose by mapping out resource needs.

Option B is incorrect because ranking activities by importance is not a primary function of the change plan; prioritization may occur, but it's not the focus. Option C is also incorrect--while the change plan aligns with the project plan, its primary value is not to update the overall project plan but to support the change management effort specifically.
Extract from SAP OCM Concepts: The change plan aligns with SAP Activate's emphasis on structured preparation and execution, ensuring resources and activities are managed effectively (SAP Activate Methodology, Change Management Workstream).



What is the added value of a high-level change impact analysis?
Note: There are 3 correct answers to this question.

  1. It reveals key project risks that can be integrated into the project's risk management at an early stage.
  2. It provides an initial systematic overview of the amount and the nature of the upcoming changes.
  3. It enables the project manager to identify opponents in highly impacted units and adjust the stakeholder analysis accordingly.
  4. It allows the change manager to derive appropriate activities, focusing the resources on key action areas.
  5. It delivers input for communication activities, making the implications of the project more tangible.

Answer(s): A,B,D

Explanation:

A high-level change impact analysis (CIA) is conducted early in an SAP project (typically in the Prepare or Explore phase of SAP Activate) to assess the scope and scale of changes. Option A is correct because identifying risks (e.g., resistance or resource gaps) early allows integration into the project's risk management strategy. Option B is correct as it provides a broad overview of change impacts across business units, processes, and people, setting the stage for detailed analysis later. Option D is correct because it helps the change manager focus efforts on high-impact areas, such as training or communication for affected groups. Option C is incorrect--while it may indirectly highlight resistance, identifying opponents is a function of stakeholder analysis, not the CIA's primary purpose. Option E is also incorrect; communication inputs are derived from the CIA but are not its core added value--tangible implications are a byproduct, not the focus. Extract from SAP OCM Concepts: The high-level CIA aligns with SAP Activate's Prepare phase, providing a foundation for risk mitigation and resource allocation (SAP Activate, OCM Framework).



What are typical topics for a change assessment at the beginning of an SAP cloud implementation?
Note: There are 3 correct answers to this question.

  1. The change culture of the company
  2. The scope for change management
  3. The cloud project's vision and expected benefits
  4. The company's change management capabilities
  5. The assessment of the key stakeholders' attitude towards the project

Answer(s): A,D,E

Explanation:

A change assessment at the start of an SAP cloud project (typically in the Prepare phase) evaluates the organization's readiness for change. Option A is correct because understanding the company's change culture (e.g., openness to innovation) sets the tone for the approach. Option D is correct as it assesses the organization's existing change management capabilities (e.g., skills, tools), identifying gaps to address. Option E is correct because gauging stakeholders' attitudes (e.g., support or resistance) is critical for planning engagement strategies. Option B is incorrect--defining the scope of change management is an outcome of the assessment, not a topic itself. Option C is also incorrect; the project vision and benefits are defined by project leadership, not assessed as part of the change assessment.
Extract from SAP OCM Concepts: The change assessment in SAP Activate's Prepare phase focuses on readiness factors like culture, capabilities, and stakeholder perspectives (SAP OCM Framework).



How would you assign the responsibilities for organizational change management in a cloud project?
Note: There are 2 correct answers to this question.

  1. In large projects, the change management responsibility is usually assigned to a designated change manager or a change management team.
  2. In mid-size projects, the change management responsibility should be assigned to the business leaders of the impacted units.
  3. In small projects, the project manager can take over the change management responsibility.
  4. Independently from the project size, the change management responsibility is assigned to the project sponsor.

Answer(s): A,C

Explanation:

Responsibility assignment in SAP OCM depends on project scale. Option A is correct because large projects require specialized expertise, so a dedicated change manager or team is typical to handle complexity. Option C is correct as small projects often lack resources for a separate change manager, so the project manager assumes this role. Option B is incorrect--business leaders may support change but are not typically responsible for managing it, as this requires specific OCM skills. Option D is incorrect; the project sponsor provides oversight and support, not direct responsibility for execution, regardless of size.
Extract from SAP OCM Concepts: SAP Activate recommends tailoring OCM roles to project size, with dedicated resources for large implementations and consolidated roles for smaller ones (SAP OCM Framework).



What are possible options for setting up organizational change management in the project organization?
Note: There are 3 correct answers to this question.

  1. As a separate project
  2. As a cross-topic
  3. As part of the functional sub-projects
  4. As a subproject
  5. As a staff unit

Answer(s): B,D,E

Explanation:

OCM can be integrated into an SAP project in various ways. Option B is correct because treating OCM as a cross-topic ensures it spans all project areas (e.g., communication, training), aligning with SAP Activate's holistic approach. Option D is correct as a subproject allows OCM to have its own plan and resources under the main project. Option E is correct because a staff unit (e.g., reporting to the project lead) provides dedicated support without separate project status. Option A is incorrect-- OCM is rarely a standalone project, as it supports the main implementation. Option C is also incorrect; embedding OCM in functional sub-projects dilutes its focus across technical areas. Extract from SAP OCM Concepts: SAP Activate supports OCM as a cross-functional, subproject, or staff function to ensure alignment with project goals (SAP OCM Framework).



In the SAP Activate Explore phase, the project team conducts fit-to-standard workshops to identify gaps between business requirements and the SAP best practice standard.
Which change management challenge is typical for this phase?

  1. Some project team members have never heard of organizational change management.
  2. Some business users do not adopt the new cloud solution.
  3. Some managers show resistance towards the cloud standard.
  4. Some business departments do not feel well prepared for the go-live.

Answer(s): C

Explanation:

During the Explore phase, fit-to-standard workshops focus on aligning business processes with SAP's best practices, often revealing changes to current ways of working. Option C is correct because managers may resist the cloud standard if it reduces customization or control, a common challenge in this phase. Option A is incorrect--lack of OCM awareness is more typical in the Discover or Prepare phase. Option B is incorrect; user adoption issues emerge post-go-live (Run phase), not in Explore. Option D is also incorrect; go-live readiness concerns arise in the Deploy phase, not Explore. Extract from SAP OCM Concepts: Resistance to standardization is a key challenge in the Explore phase, requiring targeted stakeholder engagement (SAP Activate, OCM Workstream).



Which advice fosters a successful delivery of change communication activities?
Note: There are 2 correct answers to this question.

  1. Go for a good communication mix.
  2. Don't overcommunicate.
  3. Focus on digital communication channels.
  4. Develop a compelling, comprehensive change story.

Answer(s): A,D

Explanation:

Effective change communication in SAP projects balances reach and clarity. Option A is correct because a mix of channels (e.g., emails, workshops, videos) ensures broad coverage and suits different preferences. Option D is correct as a compelling change story articulates the "why" and "what" of the project, fostering buy-in. Option B is incorrect--while overcommunication can overwhelm, the advice to "not overcommunicate" lacks specificity and isn't a proactive strategy. Option C is also incorrect; over-reliance on digital channels may exclude non-digital users and isn't universally effective.
Extract from SAP OCM Concepts: SAP OCM emphasizes a varied communication approach and a strong narrative to drive engagement (SAP OCM Framework).



What are success factors for the different dimensions of the change management framework?
Note:
There are 3 correct answers to this question.

  1. Regarding change realization, it is important to actively support the business units in the development of a new operating model.
  2. Regarding change strategy, it is important to fulfill the expectations towards change management.
  3. Regarding change leadership, it is important to establish stakeholder management as an ongoing activity.
  4. Regarding change effectiveness, it is important to use a balanced combination of change effectiveness measures.
  5. Regarding change communication, it is important to develop a compelling, comprehensive change story.

Answer(s): A,C,D

Explanation:

SAP's OCM framework includes dimensions like realization, leadership, and effectiveness. Option A is correct because change realization involves supporting business units to adopt new models post-

implementation. Option C is correct as change leadership requires ongoing stakeholder management to sustain support. Option D is correct because effectiveness relies on diverse metrics (e.g., adoption rates, satisfaction) to assess impact. Option B is vague and not a specific success factor--meeting expectations is an outcome, not a driver. Option E, while important, is a communication tactic, not a framework-wide success factor.
Extract from SAP OCM Concepts: Success factors in SAP OCM include support for realization, continuous leadership, and robust effectiveness measures (SAP OCM Framework).