The probability technical success filed is enabled for questionnaires. You have defined a questionnaire for portfolio items In customizing. When you want to fill out the questionnaire for the probability technical success filed an error message is displayed.
What is the reason for the error message?

  1. The field service configuration of the item is missing
  2. The master switch for the interface settings for questionnaires it turned off
  3. The probability technical success field is configured as read only in the field control
  4. The field service configuration of the parent bucket of the item is missing

Answer(s): D



How do you make a decision point field a required field for a specific portfolio item?

  1. Make the filed a required field for the decision point and assign the item type to the portfolio In customizing
  2. Make the filed a required field for the combination point and assign the item and decision point in customizing for the portfolio type
  3. Make the filed a required field for the combination of the item and decision point in customizing for the portfolio type
  4. Make the field a require field for the combination of decision point and portfolio type in customizing for the item type

Answer(s): C



Which of the following can you use to create multiple portfolio items simultaneously?

  1. Item template
  2. Primavera import
  3. Microsoft Excel import
  4. Microsoft project import

Answer(s): A



In portfolio management to which of the following does the logical system refer In the definition of the PS project definition object link?

  1. BCV system for reporting
  2. Target system for integration
  3. Business intelligence (BI) system for reporting
  4. Web server for integration

Answer(s): B