What innovation management object is linked to SAP portfolio and project management (PPM) out of the box?

  1. Opportunity
  2. Idea
  3. Campaign
  4. Request

Answer(s): B



How are groups linked to categories in capacity planning?

  1. A group is directly linked to one category
  2. A group is directly linked to multiple category
  3. A group is linked to multiple categories via view
  4. A group is linked to one category via view

Answer(s): A



Which system behaviour are enabled when a create a project with multiple phase? NOTE: There are 2 correct answers to this question.

  1. Determination of the start-dates of subsequent phases
  2. Rollup of activity cost allocations to phases
  3. Rollup of resource requirements of tasks to phases
  4. Determination of the start- and end-dates of tasks

Answer(s): A,D



Your client wants to add additional checklist items to a project that has already began. They want to control the items separately as unplanned.
Which setting must you make in customizing?

  1. Create a checklist type and assign a new status Unplanned
  2. Create a checklist item type and set the issue item indicator
  3. Create a checklist item type and assign to the project type
  4. Create a checklist type and set the issue list indicator

Answer(s): D