Based on which of the following the checking control function determines whether an order type will be checked and if so, which checking rules should be used?

  1. Status
  2. Scope
  3. Group
  4. Check indicator

Answer(s): A



Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.
Which of the following costs can be planned?

  1. Cost element level
  2. Each material
  3. Each internal activity
  4. Internal service

Answer(s): A,B,C



Which of the following cost planning transactions are related to Account assignment?

  1. Invoice posting
  2. Goods movement
  3. Confirmations
  4. Purchase requisitions

Answer(s): A,C,D



Which method of revenue planning allows you to follow the same procedure as in hierarchical cost planning or can be entered by revenue element?

  1. Manual planning in billing elements in the project structure
  2. Sales order planning
  3. Billing plan in project billing elements
  4. Hierarchical billing plan

Answer(s): A