In which type of billing the total value to be billed is apportioned to individual dates in the billing plan according to defined rules?

  1. Rule based billing plan
  2. Milestone billing
  3. Task based billing
  4. Activity billing

Answer(s): B



What are the three tables that are defined for order type in network costing?

  1. Each order type
  2. Each order type and plant
  3. Network profile
  4. Each plant

Answer(s): A,B,C



In which of the following ways Open PS allows you to exchange data directly with MS project?

  1. Create a project in MS project from an SAP PS project
  2. Transfer a project from MS project to SAP PS
  3. Download MS project and Upload to SAP PS
  4. Reconcile data from a project in Microsoft Project with a project in SAP PS

Answer(s): A,B,D



Which type of network does not allow you to assign materials directly, but only indirectly using a bill of materials?

  1. Operative network
  2. Task network
  3. Standard network
  4. Internal network

Answer(s): C