Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing.
In this scenario planned costs are determined for which of the following?

  1. Primary costs for general costs activities
  2. Primary costs for material components
  3. Primary costs for service activities
  4. Activity inputs for internally-processed activities

Answer(s): A,B,D



Which function of budgeting allows you to transfer any funds not used up in the previous fiscal year to the budget of the new fiscal year?

  1. Budget release function
  2. Budget carry forward function
  3. Budget transfer function
  4. Budget Return function

Answer(s): B



Which of the following helps you to adjust cost planning to changing circumstances during the execution phase of the project?

  1. Progress analysis
  2. Cost forecasts
  3. Overhead costs
  4. Interest forecast

Answer(s): B



Which of the following cannot be entered when using service activities in networks for planned and unplanned services?

  1. Goods receipt
  2. Goods issue
  3. Service entry
  4. Service acceptance

Answer(s): B



How do you evaluate and display details of orders and networks that create capacityrequirements at the work centers?

  1. Standard overview
  2. Capacity detail list
  3. Variable overview
  4. Tabular overview

Answer(s): B