Free SAP C_TPLM22_64 Exam Questions (page: 6)

Which statements about project coding mask are true?

  1. You must always use a project coding mask for your projects.
  2. The project coding mask can begin with a numerical key.
  3. The project coding mask can be shortened later, even if projects have already been created with this project coding mask.
  4. In project number maintenance, special characters are automatically determined using the project coding mask.
  5. You can lock a project coding mask for standard projects or operative projects.

Answer(s): B,D,E



You have implemented automatic requirements grouping for projects. Once you check the materials turbine and fittings you realize that the requirements are grouped for turbine but not for fittings. What might be the reason?

  1. The grouping indicator of the top WBS element is set to a single MRP Group.
  2. The network is set to no grouping for specific MRP Groups.
  3. The MRP Group for fittings is deactivated for grouping.
  4. The project definition is set to no project stock.

Answer(s): C



If the available user-definable fields do not satisfy your requirement, you have an option to develop additional fields for which of the following.

  1. WBS elements
  2. Project definition
  3. Activities
  4. Tasks

Answer(s): A,B



What happens if the appended indicator is not set and an order is appended?

  1. Order planned value is not added to the WBS planned value
  2. Order planned value is deducted from the WBS planned value
  3. Order planned value increases the WBS element planned value
  4. Order planned value is multiplied to the WBS element planned value

Answer(s): A