How can you distinguish between service activities and external activities while accessing the detailed information for service activities on the external tab page?

There are 2 correct answers to this question.

Response:

  1. Control key
  2. Service exits indicator
  3. Order unit
  4. Cost element

Answer(s): A,B



To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?

There are 2 correct answers to this question.

Response:

  1. Billing element
  2. Cost element
  3. Pricing element
  4. Account assignment element

Answer(s): A,D



In which check does only receipts that are booked before a requirement (issue) are included in the check for this issue?

Please choose the correct answer.

Response:

  1. Available to promise check
  2. Available on booking check
  3. Available on requirement check
  4. Immediate delivery check

Answer(s): A



Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis?

Please choose the correct answer.

Response:

  1. Trend technique
  2. Project technique
  3. Milestone technique
  4. Period indicator technique

Answer(s): C



Which combination allows you to assign the material components in one WBS element to different grouping WBS element?

There are 2 correct answers to this question.

Response:

  1. Plant
  2. Material group
  3. MRP group
  4. WBS group

Answer(s): A,B,D



Viewing page 2 of 34
Viewing questions 6 - 10 out of 165 questions



Post your Comments and Discuss SAP C_TPLM22_67 exam prep with other Community members: