Free SAP C_TPLM22_67 Exam Braindumps (page: 3)

Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?
Please choose the correct answer.

Response:

  1. Internally-processed activities
  2. Externally-processed activities
  3. Service activities
  4. Scheduled activities

Answer(s): C



Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.

What is the status that must be set before you can enter actual start and actual end dates?

There are 2 correct answers to this question.

Response:

  1. Partially released
  2. Released
  3. Partially set
  4. Partially finished

Answer(s): A,B



In your project, you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of the earliest scheduled dates.How can you implement this?

Please choose the correct answer.

Response:

  1. Deactivate actual date consider indicator in Parameters for Network Scheduling.
  2. Deactivate the shift order indicator in Parameters for Network Scheduling.
  3. Activate the actual date consider indicator in Parameters for Network Scheduling.
  4. Activate the shift order indicator in Parameters for Network Scheduling.

Answer(s): B



Which type of billing is generally used in plant engineering and construction projects?

Please choose the correct answer.

Response:

  1. Periodic billing
  2. Project billing
  3. Milestone billing
  4. Fixed billing

Answer(s): C



Viewing page 3 of 42
Viewing questions 9 - 12 out of 165 questions