You can you use capacity availability checks for production orders, which settings have to be made for this?Note: There are 2 Correct answers to this question?
Answer(s): A,C
To use capacity availability checks for production orders, you need to make the following settings:The relevant for finite scheduling indicator must be set for the work centers or resources that you want to check. This indicator determines whether the system considers the capacity of the work center or resource during the capacity availability check and finite scheduling. You can set this indicator in the work center or resource master data, or in the routing or production version of the order.An overall profile must be assigned in the checking control for the order type and plant. The overall profile defines the parameters for the capacity availability check, such as the period profile, the selection profile, the checking horizon, and the reaction. You can assign the overall profile inCustomizing for Capacity Planning under Availability Check -> Checking Control.
1: SAP Help Portal: Work Center/Resource2: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 5: Master Data3: SAP Help Portal: Checking Control4: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 9: Capacity Planning
What does the material type influence?Note: There are 2 correct answers to this question.
The material type is a key attribute that classifies materials according to their characteristics and determines how they are processed in the system. The material type influences the following aspects of material management:Which material master screens appear and in which sequence: The material type controls which fields are required, optional, or hidden in the material master record. It also determines the order in which the screens are displayed when creating or changing a material master record. Different material types may have different views and fields depending on the business requirements. For example, a raw material may have a purchasing view, while a finished product may have a sales view. Whether the material is produced in-house, procured externally, or both: The material type defines the procurement type of the material, which indicates how the material is procured. The procurement type can be in-house production, external procurement, or both. The procurement type affects the planning and execution of the material requirements. For example, a material with in- house production procurement type will generate planned orders, while a material with external procurement type will generate purchase requisitions or schedule lines. The material type does not influence the following aspects of material management:Which document types and class categories are allowed: The document type is a key attribute that classifies documents according to their business purpose and determines how they are processed in the system. The document type controls the number range, field selection, and status profile of the document. The document type is independent of the material type and can be used for any material type. For example, a purchase order document type can be used for any material type that is procured externally. The class category is a key attribute that classifies classes according to their application area and determines how they are processed in the system. The class category controls the characteristics, object types, and inheritance rules of the class. The class category is independent of the material type and can be used for any material type. For example, a material class category can be used for any material type that has characteristics. Which plant-specific and plant-independent statuses are allowed: The status is an attribute that indicates the current condition of an object in the system. The status can be plant-specific or plant- independent, depending on whether it applies to a specific plant or to all plants. The status is independent of the material type and can be used for any material type. For example, a material can have a plant-specific status of blocked for quality reasons, or a plant-independent status of discontinued.
Material Type | SAP Help Portal, Material Master (LO-MD-MM) | SAP Help Portal, Document Types | SAP Help Portal, [Class Category | SAP Help Portal], [Status Management | SAP Help Portal]
You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?
Answer(s): B
Consumption-based planning is a planning procedure that uses past consumption data to calculate the future requirements of materials. It does not consider the dependent requirements of higher- level materials, but only the independent requirements from sales orders, forecasts, or stock transfers. Consumption-based planning is suitable for B and C materials, which have low value, low demand variability, and high availability. Consumption-based planning reduces the planning efforts for these materials, as it does not require the maintenance of BOMs, routings, or production versions. Consumption-based planning can be further divided into reorder point planning, forecast- based planning, and time-phased planning, depending on the method of determining the reorder point and the lot size12
Consumption-Based Planning - SAP Help PortalSAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 3: Material Requirements Planning, Section 3.1: Planning Procedures, Page 67
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA? Note: There are 2 correct answers to this question.
Answer(s): B,C
The tabular planning table for capacity planning provides two chart types: the capacity requirements chart and the work center capacities chart. The capacity requirements chart displays the capacity requirements for one or more orders, grouped by order, operation, or work center. The work center capacities chart displays the available capacity and the capacity requirements for one or more work centers, grouped by work center, capacity category, or shift sequence. You can switch between these chart types using the menu options Settings -> Chart type.
Planning Table (tabular form), Capacity planning table
How can you characterize dependent requirements in material requirements planning? Note: There are 2 correct answers to this question.
Dependent requirements are the requirements for components that are derived from the requirements for the finished product or assembly. They are created when an independent requirement is created for the finished product or assembly, such as a planned independent requirement, a sales order, or a stock transport order. They are also created on assembly level during the planning run, when the system explodes the bill of material (BOM) of the finished product or assembly and calculates the requirements for the components based on the BOM structure and quantity. Dependent requirements can be created for multilevel or single-level BOM structures, depending on the planning strategy and the BOM explosion level.
Dependent Requirements | SAP Help Portal, Material Requirements Planning (PP-MRP) | SAP Help Portal.