Free SAP C_TS422_2023 Exam Braindumps (page: 7)

During production order creation, several valid production versions are found. How does the system choose the production version?

  1. Lot size or material cost
  2. Validity period or sales order
  3. Planned order or material number
  4. Alphanumeric or quota arrangement

Answer(s): B

Explanation:

The system chooses the production version based on the validity period and the sales order. The validity period determines whether the production version is valid for the planned start date of the production order. The sales order determines whether the production version is assigned to a specific sales order item or not. If there are multiple production versions that meet these criteria, the system chooses the one with the lowest alphanumeric value.


Reference:

[SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 113; [SAP Help Portal: Production Version]



What data can you maintain in the subitems of a bill of material (BOM)?
Note: There are 2 correct answers to this question.

  1. Installation point
  2. Item type
  3. Quantity
  4. Scrap percentage

Answer(s): C,D

Explanation:

The subitems of a bill of material (BOM) are the components that make up the product or assembly. You can maintain the following data for each subitem:
Quantity: This is the number of units of the component that are required for one unit of the product or assembly. You can specify the quantity in different units of measure, such as base unit, order unit, or alternative unit. You can also use variable quantities, such as percentages or formulas, to calculate the quantity dynamically based on the product or assembly characteristics. Scrap percentage: This is the percentage of the component that is expected to be wasted or lost during the production or assembly process. You can specify the scrap percentage for each component to adjust the quantity accordingly. For example, if the quantity of a component is 10 and the scrap percentage is 5%, the system will increase the quantity by 0.5 to account for the scrap. The installation point (A) and the item type (B) are not data that you can maintain in the subitems of a BOM. The installation point is a field in the equipment master record that indicates where the equipment is installed. The item type is a field in the sales document item that determines the processing and pricing of the item. These fields are not relevant for the BOM subitems.


Reference:

https://sapstack.com/pp/bom-in-sap-bill-of-material/
https://skillstek.com/bill-of-material-in-sap/



Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

  1. Use a propagation range.
  2. Use a resource group
  3. Use a planning area.
  4. Use a planning group.

Answer(s): B

Explanation:

You can achieve planning only for specific resources in Advanced Planning (PP/DS) by using a resource group. A resource group is a collection of resources that share the same characteristics and can be used interchangeably for production. You can assign a resource group to a product or a production version, and then use the resource group as a selection criterion in the planning board or the product view. This way, you can restrict the planning to only those resources that belong to the resource group.


Reference:

SAP S/4HANA Manufacturing for Planning & Scheduling - Implementation Guide, page 25; [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 79.



in your Plant, MRP is activated.
which options do you have to exclude a material from the MRP run?

Note: there are 2 correct answers to this question.

  1. Use a specific material status
  2. Use a specific material group
  3. Use a specific MRP type
  4. Use a specific MRP list

Answer(s): A,C

Explanation:

You can exclude a material from the MRP run by using a specific material status or a specific MRP type. A material status is a user-defined indicator that can be assigned to a material master record to control the procurement and planning activities for the material. For example, you can define a material status that blocks the material from being planned by MRP. An MRP type is a parameter that defines how a material is planned by MRP. For example, you can use the MRP type ND (No Planning) to exclude the material from the MRP run.


Reference:

[SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 87; [SAP Help Portal: Material Status] and [SAP Help Portal: MRP Type].



Viewing page 7 of 21
Viewing questions 25 - 28 out of 80 questions



Post your Comments and Discuss SAP C_TS422_2023 exam prep with other Community members:

C_TS422_2023 Exam Discussions & Posts