Which of the following values can be calculated using results analysis? 3 answers

  1. Work in progress
  2. Reserves for unrealized costs
  3. Cost of sales
  4. Cost of goods manufactured
  5. Gross margin

Answer(s): A,B,C



How doesSAP S4HANA select line-item-based data for costing-based Profitability Analysis reports ?

  1. It selects data from table ACDOCA and plan data from table ACDOCP
  2. It selects data from table CE1XXXX and plan data from table CE2XXXX
  3. It selects datafrom table CE2XXXX and plan data from table CE3XXXX
  4. It selects data from table ACDOCA and plan data from table COSP

Answer(s): B



Where can youfind actual transaction data of account-based CO-PA in SAP S/4HANA?

  1. BSEG
  2. CE1XXXX
  3. COEJ
  4. ACDOCA

Answer(s): D



You post an expense line in an accounting document and enter an internal order and a cost center as the account assignments. After posting, the system allows you to settle the posted values from the internal order. Which settings do the cost center and internal order have?

  1. Real internal order
    Statistical cost center
  2. Statistical internal order
    Real cost center
  3. Statistical internal order
    Statistical cost center
  4. Real internal order
    Real cost center

Answer(s): D



At what level do you create the structure of the operating concern?

  1. Client level
  2. Sales organization level
  3. Company code level
  4. Controlling area level

Answer(s): A