SAP C_TSCM42_67 Exam
SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 (Page 11 )

Updated On: 9-Feb-2026

A user you advise wishes to transfer variable process instructions for automated processing directly to certain work centers and machines in the production department (for example, feed speed, pressing pressure, dry temperature). The user also wishes to receive variable as-is messages (such as actual quantities, actual times) from these work centers and machines and to process these messages for feedback concerning production orders. Which of the following options would you recommend to implement these requirements?

  1. Execution Steps (XSteps) and process messages
  2. SAP Business Intelligence (BI)
  3. Plant data collection (PP-PDC) interface
  4. SAP Application Link Enabling (ALE)

Answer(s): A



In SAP ECC, you want to map an in-house production process for general warehouse production. The fields in the area of the lot size-dependent in-house production time are to be populated when the material master for the final product is created. These fields can be maintained by updating from the scheduling result for the associated routing. You now think that there could be significant changes to the production times in the routing and decide against updating the material master. What problem could this lead to?

  1. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
  2. Requirements planning runs up against an exception message in basic dates scheduling because the material master parameters do not match the scheduling result from the routing.
  3. In the course of basic dates scheduling with requirements planning, dependent requirements request the components from the bill of materials at the wrong times.
  4. Lead time scheduling, which occurs by the time that a planned order is converted into a production order (at the latest), cannot take place on the basis of incorrect basic dates.

Answer(s): C



The company you advise wants to control the availability check in so that when a production and/or process order is created, the following receipts or issues are taken into account: planned orders, purchase orders, production orders, reservations, dependent requirements. When the production and/or process order is released, only the stock that is currently freely usable should be taken into consideration. How can you fulfill this request?

  1. Differentiated assignment of two different checking rules in check control.
  2. Activate the freely usable stock in the scope of check.
  3. Enter an appropriate availability checking group in the material master.
  4. Enter an appropriate availability checking rule in the order type.

Answer(s): A



Which data forms the basis for calculating the capacity requirement for an operation? (Choose three.)

  1. Standard values (routing)
  2. In-house production time (material master)
  3. Transport time (routing)
  4. Formulas (work center)
  5. Operation control key (routing)

Answer(s): A,D,E



Which of the following properties applies to multi-site planning in SAP ECC?

  1. When using one-step stock transfer posting, transfer stock is created in the receiving plant.
  2. Multi-site planning can be activated using the corresponding planning strategy.
  3. Both withdrawal from an alternative plant and stock transfer from another plant are defined via special procurement keys.
  4. The use of "scope of planning" is always mandatory for multi-site planning.

Answer(s): C






Post your Comments and Discuss SAP C_TSCM42_67 exam prep with other Community members:

Join the C_TSCM42_67 Discussion