The product backlog contains 60 story points. The team velocity is around 20 story points per iteration. How many Iterations would it take to finish the backlog?

  1. 1 Iteration
  2. 2 Iterations
  3. 4 Iterations
  4. 3 Iterations

Answer(s): D

Explanation:

60/20 = 3



When is Continuous Exploration happening?

  1. On demand, based on market rhythms and events
  2. Every Iteration
  3. During the IP Iteration in preparation for PI Planning

Answer(s): B

Explanation:

Continuous Exploration (CE) is the process that drives innovation and fosters alignment on what should be built by continually exploring market and customer needs, and defining a Vision, Roadmap, and set of Features for a Solution that addresses those needs.



Who is facilitating the Scrum of Scrums?

  1. Business Owners
  2. Scrum Master
  3. Product Owner
  4. Release Train Engineer

Answer(s): D

Explanation:

The Release Train Engineer (RTE) typically facilitates a weekly (or more frequently, as needed) Scrum of Scrums (SoS) event. The SoS helps coordinate the dependencies of the ARTs and provides visibility into progress and impediments. The RTE, representatives from each team (often the Scrum Master), and others (where appropriate) meet to review their progress toward milestones and PI objectives, and dependencies among the teams. The event is timeboxed for 30-60 minutes and is followed by a ‘meet after’ where individuals who want to do a deeper dive into specific problems can remain behind.



What are the three inputs to start PI Planning?

  1. A set of PI Objectives
  2. Product/Solution Vision
  3. Business context
  4. Solution Roadmap
  5. Top-10 Features
  6. Ready user stories

Answer(s): B,C,E

Explanation:

Program Increment (PI) Planning is a cadence-based, face-to-face event that serves as the heartbeat of the Agile Release Train (ART), aligning all the teams on the ART to a shared mission and Vision. PI Program Backlog A successful PI planning event delivers two primary outputs: Committed PI objectives – A set of SMART objectives that are created by each team with the business value assigned by the Business Owners. Program board – Highlighting the new feature delivery dates, feature dependencies among teams and relevant Milestones.



Page 6 of 22



Post your Comments and Discuss Scaled Agile SAFe-Agilist exam with other Community members:

DA commented on October 30, 2024
Very good and help a lot for practice
INDIA
upvote

Prasun Adhikary commented on September 07, 2024
This is a cool practice test!
Anonymous
upvote