A Sprint Retrospective should be held:

  1. At the end of each Sprint.
  2. At the beginning of each Sprint.
  3. Only when the Scrum Team determines it needs one.
  4. At the end of the last Sprint in a project or a release.

Answer(s): A

Explanation:

The correct answer is A, because a Sprint Retrospective should be held at the end of each Sprint. The Scrum Guide states that "the Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint. ... The Sprint Retrospective occurs after the Sprint Review and prior to the next Sprint Planning."



A new developer is having continuing conflicts with existing Development Team members and creating the hostile environment. If necessary, who is responsible for removing the team member?

  1. The hiring manager is responsible, because he/she hired the developer.
  2. The Scrum Manager is responsible, because he/she removes Impediments.
  3. The Development Team is responsible, and may need help from the Scrum Master.
  4. The Product Owner is responsible, because he/she controls the return on investment (ROI).

Answer(s): C

Explanation:

The correct answer is C, because if necessary, the Development Team is responsible for removing a team member who is creating a hostile environment. The Scrum Guide states that "development Teams are self-organizing. No one (not even the Scrum Master) tells the Development Team how to turn Product Backlog into Increments of potentially releasable functionality." Therefore, the Development Team should manage its own composition and dynamics, and may need help from the Scrum Master to facilitate this process.



Which three purposes does the definition of "Done" serve? (Choose three.)

  1. Guide the Development Team on how many Product Backlog items to select for the Sprint.
  2. Create a shared understanding of when work is complete.
  3. Describe the purpose, objecti ve, and time-box of each Scrum event.
  4. Describe the work that must be done before the Sprint is allowed to end.
  5. Increase transparency.

Answer(s): A,B,E



The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.

  1. True
  2. False

Answer(s): B

Explanation:

The correct answer is B, because the Product Owner does not make sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders. The Scrum Guide states that "the number of items selected from the Product Backlog for the Sprint is solely up to the Development Team. Only the Development Team can assess what it can accomplish over the upcoming Sprint." Therefore, the Development Team is responsible for choosing the scope of work for a Sprint.



Which statement best describes the Sprint Review?

  1. It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.
  2. It is a demo at the end of the Sprint for everyone in the organization to check on the work done.
  3. It is a mechanism to control the Development Team's activities during a Sprint.
  4. It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.

Answer(s): D

Explanation:

The correct answer is D, because this statement best describes the Sprint Review. The Scrum Guide states that "a Sprint Review is held at the end of the Sprint to inspect the Increment and adapt the Product Backlog if needed. During the Sprint Review, the Scrum Team and stakeholders collaborate about what was done in the Sprint." Therefore, the Sprint Review is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.



Viewing page 23 of 55
Viewing questions 111 - 115 out of 298 questions


Post your Comments and Discuss Scrum PSM I exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!