The Development Team should have all the skills needed to:

  1. Turn Product Backlog items into an Increment of potentially releasable product functionality.
  2. Do all of the development work, except for specialized testing that requires additional tools and environments.
  3. Complete the project within the date and cost as calculated by the Product Owner.

Answer(s): A

Explanation:

According to the Scrum Guide1, an Increment is a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together. In order to provide value, an Increment must be usable. Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review thus supporting empiricism. However, an Increment may be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value. Therefore, in order to turn Product Backlog items into an Increment of potentially releasable product functionality, the Development Team should have all the skills needed.


Reference:

Scrum Guide



The Scrum Master observes the Product Owner struggling with ordering the Product Backlog.
What is an appropriate action for the Scrum Master to take?

  1. Suggest the Product Owner extend the Sprint, so he can have more time to order the Product Backlog.
  2. Suggest that the Development Team does the ordering to be sure that it is a feasible ordering of work.
  3. Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.
  4. Present the Product Owner with an ordered Product Backlog to use.
  5. Encourage the Product Owner to work with the Development Team to see which items technically are fastest to implement.

Answer(s): C

Explanation:

According to the Scrum Guide1, ordering Product Backlog items is solely up to the Product Owner's discretion. The Product Owner orders items in the Product Backlog to best achieve goals and missions. To do this, they optimize value by considering various factors such as cost and benefit, risk, dependencies, date needed, etc. The Product Owner is responsible for maximizing the value of the work the Development Team does. The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide. They do this by helping everyone understand Scrum theory and practice, both within the Scrum Team and the organization. Therefore, an appropriate action for the Scrum Master to take if the Product Owner is struggling with ordering the Product Backlog is to offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.


Reference:

Scrum Guide



Which two things are appropriate for a Scrum Master to do if the Development Team doesn't have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Choose two.)

  1. Coach the Development Team to improve its skills, tools, and infrastructure over time and adjust the Definition of "Done" accordingly.
  2. Encourage the Product Owner to accept partially "Done" increments until the situation improves.
  3. Refocus the current Sprint on establishing the Development Team's infrastructure instead of delivering an increment.
  4. Declare the Development Team not ready for Scrum.
  5. Have the Development Team establish a Definition of "Done" that is actually possible to achieve given current circumstances.

Answer(s): A,E

Explanation:

According to the Scrum Guide1, the definition of "Done" is a formal description of the state of the Increment when it meets the quality measures required for the product. The definition guides the Development Team in creating a "Done" Increment. The definition of "Done" is created by the development organization (or Development Team if none is available from the development organization). The definition of "Done" may vary significantly per Scrum Team, depending on the context. One aspect of Scrum Teams inspecting how they work toward their Product Goal is that they improve their definition of "Done" over time. Therefore, two things that are appropriate for a Scrum Master to do if the Development Team doesn't have the engineering tools and infrastructure to completely finish each selected Product Backlog item are:
Coach the Development Team to improve its skills, tools, and infrastructure over time and adjust the Definition of "Done" accordingly.
Have the Development Team establish a Definition of "Done" that is actually possible to achieve given current circumstances.



When is implementation of a Product Backlog item considered complete?

  1. At the end of the Sprint.
  2. When the item has no work remaining in order to be potentially released.
  3. When QA reports that the item passes all acceptance criteria.
  4. When all work in the Sprint Backlog related to the item is finished.

Answer(s): B

Explanation:

According to the Scrum Guide1, an Increment is a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together. In order to provide value, an Increment must be usable. Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint

Review thus supporting empiricism. However, an Increment may be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value. Therefore, implementation of a Product Backlog item is considered complete when the item has no work remaining in order to be potentially released.



Choose two responsibilities of a self-organizing Development Team. (Choose two.)

  1. Reorder the Product Backlog.
  2. Pull Product Backlog items for the Sprint.
  3. Do the work planned in the Sprint Backlog.
  4. Increase velocity.
  5. Report daily progress to stakeholders.

Answer(s): B,C

Explanation:

The correct answers are B and C, because these are two responsibilities of a self-organizing Development Team. The Scrum Guide states that "the Development Team consists of professionals who do the work of delivering a potentially releasable Increment of `Done' product at the end of each Sprint. Development Teams are structured and empowered by the organization to organize and manage their own work." Therefore, the Development Team should pull Product Backlog items for the Sprint and do the work planned in the Sprint Backlog.