What role can configure the default columns in the project planning console? (Choose two.)

  1. admin
  2. it_pps_admin
  3. it_project_manager
  4. it_console_admin

Answer(s): A,B



A checklist item record provides a name and what other element?

  1. Status field.
  2. Percent complete field.
  3. Complete field.
  4. Short description field.

Answer(s): C



Which related lists should primarily be used to capture financial data in a project? (Choose two.)

  1. Programs
  2. Cost Plans
  3. Monetary Benefit Plans
  4. Risks

Answer(s): B,C



Which demand category would a demand manager select, if they need to create an enhancement?

  1. Defect
  2. Operational
  3. Change
  4. Strategic

Answer(s): D



In which table can you find cost information for a specific fiscal period?

  1. cost_plan_breakdown
  2. expense_line
  3. pm_project
  4. cost_plan

Answer(s): A



When copying a source project to a target project, what fields are copied by default? (Choose three.)

  1. Planned dates.
  2. Number.
  3. Short description.
  4. Duration fields.
  5. State.

Answer(s): A,C,D



Which of the following can be used to calculate planned cost when creating a resource plan? (Choose two.)

  1. Default rate
  2. Demand rate
  3. Project rate
  4. Rate card

Answer(s): A,D



On the demand form, what does the Discount Rate impact?

  1. Internal Rate of Return %.
  2. Financial Benefit.
  3. Net Present Value (NPV).
  4. ROI.

Answer(s): C



Viewing page 7 of 24
Viewing questions 49 - 56 out of 182 questions