Which one of the following INCORRECTLY matches a type of Scrum Team and a corresponding communication facilitator?

  1. Colocated Team : War Rooms
  2. Colocated Team: Wall displays
  3. Distributed Team: Video Conferencing
  4. Distributed Team : Manual Scrumboard

Answer(s): C


Reference:

https://www.atlassian.com/agile/teams/remote-teams



Which of the following are important selection criteria while choosing a Scrum Master?

  1. Leadership style, problem-solving, availability, commitment
  2. Stress management, people management, communication, loyalty
  3. Responsiveness, problem-solving, facilitator, negotiation
  4. Intuitiveness, people management, reliability, facilitator

Answer(s): A


Reference:

http://blog.scrumstudy.com/selecting-appropriate-scrum-masters-and-identifying- relevantstakeholders/



The Scrum Master coordinates with the Product Owner and other stakeholders to ensure benefits from the project are realized.
Which of the following is true about Benefits Realization?

  1. Benefits from Scrum projects are realized during Demonstrate and Validate Sprint, Conduct Release Planning, Create Deliverables, and Retrospect Sprint processes.
  2. Benefits from Scrum projects are realized during Demonstrate and Validate Sprint, Retrospect Sprint, Ship Deliverables, and Retrospect Project processes.
  3. Benefits from Scrum projects are realized during Demonstrate and Validate Project, Retrospect Sprint, Grooming Product Backlog, and Retrospect Project processes.
  4. Benefits from Scrum projects are realized during Demonstrate and Validate Project, Conduct Release Planning, Verify Deliverables, and Retrospect Sprint processes.

Answer(s): B

Explanation:

The Product Owner confirms the achievement of organizational benefits throughout the project, as well as upon completion of the User Stories in the Prioritized Product Backlog. Benefits from Scrum projects are realized during Demonstrate and Validate Sprint, Retrospect Sprint, Ship Deliverables and Retrospect Project processes.


Reference:

http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf



A Product Owner is prioritizing user Stories to create a Prioritized Product Backlog for a project to design a banking portal. All of the following User Stories will be evaluated while prioritizing EXCEPT:

  1. User Stories that generate value for the customer.
  2. User Stories that are dependent on others for completion.
  3. User Stories that are innovative and may or may not be successfully created.
  4. User Stories that are very difficult to determine its value, create and/or deliver.

Answer(s): D