The Chief Scrum Master plays an important role during the Retrospect Project process. By being a part of the Retrospect Project Meeting, he/she provides valuable inputs mainly to identify, document, and internalize the lessons learned during the process.
What is an output of this process?
- Agreed Actionable Improvements.
- Agreed Actionable Schedule.
- Agreed Actionable Lessons.
- Agreed Actionable Objectives.
Answer(s): A
Reference:
http://blog.scrumstudy.com/retrospect-scrum-project-the-lessons-to-be-learnt/