The Chief Scrum Master plays an important role during the Retrospect Project process. By being a part of the Retrospect Project Meeting, he/she provides valuable inputs mainly to identify, document, and internalize the lessons learned during the process.

What is an output of this process?

  1. Agreed Actionable Improvements.
  2. Agreed Actionable Schedule.
  3. Agreed Actionable Lessons.
  4. Agreed Actionable Objectives.

Answer(s): A


Reference:

http://blog.scrumstudy.com/retrospect-scrum-project-the-lessons-to-be-learnt/



At the end of each Sprint the Scrumboard is _________.

  1. Updated with new tasks and completed tasks.
  2. Placed besides the new one to compare team velocities in Sprints.
  3. Analyzed by the Scrum master to understand the project progress in that particular sprint.
  4. Reset or wiped off.

Answer(s): C


Reference:

https://fitsmallbusiness.com/what-is-a-scrum-board/? __cf_chl_jschl_tk__=f53936a02af8b13a6c789509a9e50d80caf9db68-1579965118-0- AX8DQIwPUTwHssRinUC0HBs1y0G4cueRRcNpGOdv3upGebf3xhz6sZtrd3r_e8p- 2LCAKsOhNtvMe1BjqhYqPiFFr1H832NeKyU9aTS7hOHZLRq68r12ibXnfqveWkOuTmmkUy0lhkGM2jW r8w-7OODeTjry5BdCU0qCXv-ci8Kv6-QAHh8LizLiiZ9a7f-
BSzwcw15OkMbF6N6O3GdgjoKH48pvA7BxNqQIfxXxSaAPc7PSgiP4JNyrYhJsGWryQdu6msOKQXrxt4sa0Dl9UEwRyjyGzD_Nyzy7_qmwi5z



Emily has taken on the role of Scrum Master on a new project. Training the team is one of her major responsibilities. As Scrum Master, which aspects will Emily need to address in this respect?

A) Gaps in technical knowledge in any of the team members.
B) Shortcomings in the Scrum Team's understanding of business value of features.
C) Increasing the team's capability to articulate their challenges to find solutions.
D) Lack of understanding of the Scrum processes and principles.

  1. B and C
  2. A, B, and C
  3. C only
  4. C and D

Answer(s): D



To enable the Product Owner to successfully deploy the product release as a part of the Ship Deliverables process, the Scrum Master should ensure that:

  1. The Scrum Team creates Deliverables as agreed upon
  2. The Release Plan and Prioritized Product Backlog are updated
  3. The Scrum Team creates the Release Planning Schedule
  4. The Scrum team Accepts/Rejects the deliverables during Demonstrate and Validate Sprint process

Answer(s): A


Reference:

http://blog.scrumstudy.com/what-is-the-role-of-the-scrum-product-owner/