Free Scrum Master Certified Exam Braindumps (page: 4)

Page 3 of 37

Program Stakeholders, the Program Product Owner, Program Scrum Master, and Chief Product Owner have gathered together to create the Project Vision. They are trying to determine and document the difference between current business capabilities and the final desired set of capabilities.

Which one of the following should they use to arrive at a conclusive decision?

  1. Trial Project.
  2. JAD Session.
  3. Gap Analysis.
  4. SWOT Analysis.

Answer(s): C


Reference:

http://blog.scrumstudy.com/tools-to-create-project-vision/



Collaboration within a team is an important principle of Scrum. All of the following activities constitute collaboration EXCEPT:

  1. The Scrum Team decides which User Stories are important and assigns which Sprint they should be worked on.
  2. The Scrum Team discusses the best approach to creating deliverables during a Sprint.
  3. A Scrum Team member is facing difficulties in one of his tasks and another team member pitches in to help him.
  4. The Scrum Team interacts with the Product Owner to obtain clarification on User Stories.

Answer(s): A


Reference:

https://www.oreilly.com/library/view/head-first-agile/9781491944684/ch04.html



While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?

  1. Length of Sprint, Agreed Actionable Improvements, Done Criteria, Team Calendar.
  2. Assigned Action Items, Business Improvements, Dependencies, Team Calendar.
  3. Length of Sprint, Previous Sprint Velocity, Dependencies, Team Calendar.
  4. Proof of Concept, Previous Sprint Velocity, Done Criteria, Team Calendar.

Answer(s): C



Which of the following methods helps estimate the value provided by projects?

  1. Internal Rate of Return
  2. Net Rate of Return
  3. Present Rate of Return
  4. Estimated Rate of Return

Answer(s): A

Explanation:

The value to be provided by business projects can be estimated using various methods such as Return on Investment (ROI), Net Present Value (NPV) and Internal Rate of Return (IRR).


Reference:

http://blog.scrumstudy.com/estimating-project-value-in-scrum/