Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories committed to for the current Sprint because the customer has changed a critical business requirement.

Which one of the following statements presents the best solution for such a situation?

  1. You should direct the Scrum team to stop working on the current Sprint Backlog, and to start working on the latest business requirements.
  2. The Product Owner should add this requirement to the overall Prioritized Product Backlog, and the team would work on it in a future Sprint.
  3. You should tell the Product Owner to inform the stakeholders that this business requirement cannot be worked on as the Scrum Team has no bandwidth in the current Sprint.
  4. The Product Owner should cancel the current Sprint, and should start planning a new Sprint for the team to be able to develop the deliverable as per the latest business requirement.

Answer(s): B



During the Form Scrum Team process, the Scrum Master must collaborate with the Product Owner to enable him or her to select the team members.
Which of following sets of Traits is desirable of a Scrum Team member?

  1. Scrum Expert, Business Domain knowledge, Highly motivated.
  2. Collaborative, Self-organizing, Negotiation skills.
  3. Business Domain knowledge, Collaborative, Cross-functional outlook.
  4. Collaborative, Highly motivated, Independent.

Answer(s): C


Reference:

https://www.smartsheet.com/scrum-team-roles-responsibilities-how-build-most- effective-scrumteam



You are a Scrum Master on a project creating an optical fiber cable network across the country. The project has reached the Create User Stories process.
Which of the following is NOT an input to this process?

  1. The Prioritized Product Backlog.
  2. Identified Risks.
  3. Personas.
  4. Done CriteriA.

Answer(s): B

Explanation:

The key inputs of creating user stories are Scrum Core Team, Prioritized Product Backlog, Done Criteria, and Personas. The most import tool is User Story Writing Expertise. And the major outputs are User Stories and User Story Acceptance Criteria.


Reference:

http://blog.scrumstudy.com/how-are-user-stories-created-in-a-scrum-project/



Which of the following is a process in the initiate phase of Scrum?

  1. Identify Scrum Master and Stakeholder(s)
  2. Estimate User Stories
  3. Conduct Daily Standup
  4. Commit User Stories

Answer(s): A


Reference:

https://www.scrumstudy.com/whyscrum/scrum-initiate



You are the Scrum Master of a project to construct an IT Tech Park. This project requires adhering to stringent quality standards at every stage of development. A Scrum Core Team is formed for this project in which the Scrum Master is supposed to facilitate a "team first" mentality when it comes to quality. You must ensure all of the following to maintain quality in Scrum, EXCEPT:

  1. Any quality related error must be fixed only at the end to ensure that the deliverable is Done.
  2. Iterative Product development, repetitive testing, and documentation help ensure quality is
    inherent in each Done deliverable.
  3. Any quality requirement must consider the capacity and willingness of the organization to meet the business need.
  4. The changing needs of the customers must be incorporated during the increments.

Answer(s): A



Viewing page 7 of 31
Viewing questions 31 - 35 out of 147 questions