What is the result of a forward pass calculation?

  1. Value of total float for individual activities
  2. Early start and early finish date for individual activities
  3. Value of free float for individual activities
  4. Critical path

Answer(s): B



Which of the following is NOT input data to the construction planning process?

  1. Input from the owner
  2. The contract
  3. Bonding capacity of subcontractors
  4. Input from the contractor

Answer(s): C



Project schedules help control all of the following EXCEPT for_____________________.

  1. Quality
  2. Cost
  3. Resources
  4. Time

Answer(s): A



When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

  1. Detailed listing of working days for each calendar used
  2. Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID
  3. Assigned party responsibility for each work task
  4. Tabular listing of activities showing duration, calendar ID, early and late dates

Answer(s): C