______________ is the sum of queue, setup, run, wait and move times at work center.

  1. Work center times
  2. Production times
  3. Lead time
  4. Order to delivery time

Answer(s): C



Following is an example of:

  1. Wait time schedule
  2. Lead time schedule
  3. Shop calendar
  4. Routing file

Answer(s): C



Which one of the following affects capacity available?

  1. Product specifications
  2. Product Mix
  3. Plant and equipment and work effort
  4. All of these

Answer(s): D



____________ and _____________ depends on the design of the product and the mix of the products made.

  1. Product specification and product mix
  2. Product specification and product quality
  3. Product quality and product line
  4. Product demand and ordered quantity

Answer(s): A



It provides a yard stick for measuring work content and unit for stating capacity. What is it?

  1. Work effort
  2. Standard time
  3. Lead time
  4. Move time

Answer(s): B