Capacity needs to be measured on following levels EXCEPT:

  1. Machine or individual
  2. Work center
  3. Plant, which can be considered as a group of different work centers
  4. None of these

Answer(s): D



There are two ways to determining the capacity available; out of which __________ is figured from historical data and ___________ is based on available time, utilization and efficiency.

  1. Demonstrated, calculated capacity
  2. Measured, rated capacity
  3. Both A and B are same
  4. Measured, demonstrated capacity

Answer(s): C



A work center working one 8 hour shift for 5 days a week is available _____________ hours a week is available

  1. 40 hours
  2. 35 hours as lunch timings
  3. 45 hours
  4. 30 hours

Answer(s): A



A work center has 3 machines and is operated for 8 hours a day and 5 days a week. What is the available time?

  1. 100 hours per week
  2. 80 hours per week
  3. 90 hours per week
  4. 120 hours per week

Answer(s): D



A work center is available 120 hours but actually produced goods for 100 hours. What is the utilization of the work center?

  1. 84.3%
  2. 84%
  3. 83.3%
  4. 83.5%

Answer(s): C