The plan must be checked against available capacity when needed to make the components is called the process of

  1. Capacity Requirement planning
  2. Material Requirements planning (MRP)
  3. Production Activity control (PAC)
  4. A & C

Answer(s): A



The computer software program that organizes and maintains the bills of material structures and their linkage is called:

  1. Inventory record
  2. Purchasing record
  3. Bills of material processor
  4. Procurement of material and supplies

Answer(s): C



Master production schedule, inventory records and bills of material are three major inputs to

  1. Material Requirements planning (MRP) System
  2. Production activity Control
  3. Manufacturing Planning and Control (MPC) Function
  4. Capacity Requirements planning (CRP)

Answer(s): A



Master Production schedule:

  1. A statement of which end items are to be produced, the quantity of each, and the dates they are to be completed
  2. Drives the MRP system by providing the initial input for the items needed
  3. Both A, B
  4. None of the above is true

Answer(s): C



Inventory Record is one of the major input to the

  1. Capacity Requirements planning (CRP)
  2. Material Requirements planning (MRP) System
  3. Manufacturing Planning and Control (MPC) Function
  4. Production activity Control

Answer(s): B