Which of the following aspects would best describe part of the project environment?

  1. The influence and interests of the key stakeholders of the project.
  2. The technical difficulties that are anticipated when undertaking the project.
  3. The circumstances within which the project is being undertaken.
    D The relationship between the project manager and the project team.

Answer(s): C



What would be a most likely result for an organisation following a PESTLE analysis?

  1. The organisation would know what political change is most likely and therefore the impacts on objectives considered.
  2. The organisation would most likely have a number of options available as to how the desired objectives could be achieved.
  3. The organisation would have an understanding of the necessary skills required to deliver the objectives required.
    D The organisation would be able to develop an accurate estimate of the costs and time frame for the objectives to be achieved.

Answer(s): B



Which of the following is true of the project environment?

  1. Within the environment are the factors that influence and impact projects.
  2. Only certain types of projects are influenced by the environment.
  3. The project environment will only really impact the project at the start.
    D There is no real way of determining the true project environment.

Answer(s): A



Why is environmental analysis the most important analysis for an organisation to undertake?

  1. It allows the detailed execution plans, to be defined, that are likely to be developed in order to deliver the project.
  2. It is the only way in which the scope of the project can be identified and detailed in plans.
  3. It identifies the problems, opportunities or business needs which may require some degree of response.
    D It is the only form of detailed planning that can be carried out in the earliest phases of the project life cycle.

Answer(s): C



What is the most likely conclusion resulting from a PESTLE analysis?

  1. The agreed end date for the project.
  2. A list of possible stakeholders.
  3. The number of project phases necessary.
    D The size of the project team required.

Answer(s): B