The project team comprises:

  1. all those responsible to the project manager who are working towards the project objectives.
  2. the members of staff who are allocated full time to the project.
  3. the members of staff who report to the project manager and who carry out work on the project.
  4. all project stakeholders.

Answer(s): A



Good teamwork helps to deliver a successful project because:

  1. team members have similar skill sets.
  2. project work can be distributed equally around the team.
  3. all team members have the same access to project information.
  4. people work collaboratively towards a common goal.

Answer(s): D



Which one of the following is NOT a function of leadership?

  1. Reinforcing positive relationships.
  2. Inspiring the individual.
  3. Maintaining constant tight control.
  4. Promoting the project vision.

Answer(s): C



PESTLE analysis covers the following areas:

  1. Political, Economic, Sociological, Technical, Legal, Environmental.
  2. Personnel, Economic, Safety, Technical, Legal, Ecological.
  3. Political, Ecological, Strategy, Technical, Life cycle, Environmental.
    D Personnel, Ecological, Sociological, Training, Life cycle, Ecological.

Answer(s): A



Which of the following best describes a project's context?

  1. The environment in which the business operates.
  2. The geographic location in which the project is undertaken.
  3. The external and internal business environments including stakeholder's interests and influences.
    D Industry and business sector practices.

Answer(s): C



Viewing page 41 of 83
Viewing questions 201 - 205 out of 354 questions