Free APM-PFQ Exam Braindumps
APM Project Fundamentals Qualification Questions 191–195 (page: 40)

Updated On: 10-Feb-2026

The project manager's prime responsibility is to:

  1. deliver the benefits.
  2. define the requirements.
  3. sign off the business case.
  4. implement the project plan

Answer(s): D



Which one of the following best describes the purpose of a project's business case?

  1. A statement of what the project will deliver in terms of products/deliverables and satisfaction.
  2. The reasons why the project sponsor wants their project to proceed.
  3. A statement on how the project fits into the long-term aims of the project sponsor.
  4. Provides justification for undertaking the project, in terms of evaluating the benefits, cost and risks

Answer(s): D



What is the term given to the senior management team that set the strategic. direction for a project?

  1. Project management office.
  2. Change control board.
  3. Project steering group.
  4. Programme director.

Answer(s): D



Which one of the following statements best describes communication?

  1. The giving, receiving, processing and interpretation of information.
  2. The explanation, understanding, managing and sorting of information.
  3. The giving, explaining, understanding and interpretation of information.
  4. The managing, receiving, processing and sorting of information.

Answer(s): A



A project communication plan identifies the relevant information that should be communicated to:

  1. the project team.
  2. the project stakeholders.
  3. the project board.
  4. the project sponsor

Answer(s): B