ASQ CSSBB Exam
CSSBB Certified Six Sigma Black Belt (Page 8 )

Updated On: 15-Feb-2026

A project that lacks a clear definition of its scope and boundaries runs the risk of:

  1. straying from the intended path
  2. trying to solve unrelated problems
  3. having difficulty in collecting baseline data
  4. suffering morale problems
  5. all the above
  6. none of the above

Answer(s): E



The primary metric for a project is reduced cost for process A .A consequential metric could be:

  1. reduced cycle time
  2. reduced scrap rate
  3. reduced set-up time
  4. all the above
  5. none of the above

Answer(s): D



The primary metric for a project is reduced cost for process A . Baseline data might include:

  1. current maintenance costs
  2. current selling price for the products or services output by process A
  3. current suggestions from stakeholders of process A
  4. all the above
  5. none of the above

Answer(s): A



According to the Central Limit Theorem:

  1. the median and the mean have the same value in a symmetric distribution
  2. the mode of a normal distribution is also the mean
  3. the mean of an exponential distribution is smaller than the median
  4. the mean, median and mode of a normal distribution all have the same value
  5. none of the above

Answer(s): E



The term “expected value” is closest to the term:

  1. median
  2. probabilistic model
  3. mean
  4. Markov value
  5. regressive value

Answer(s): C






Post your Comments and Discuss ASQ CSSBB exam prep with other Community members:

Join the CSSBB Discussion