There are 14 different defects that can occur on a completed time card. The payroll department collects 328 cards and finds a total of 87 defects. DPMO =:

  1. 87 ÷ 328
  2. 87 ÷ (328 × 14)
  3. 14 ÷ 87
  4. 87 ÷ 14 × 1,000,000
  5. 328 ÷ 87
  6. 87 × 1,000,000 ÷ (14 × 328)

Answer(s): F



A random sample of 2500 printed brochures is found to have a total of three ink splotches. The rate of ink splotches in PPM is:

  1. 1,000,000 ÷ 2500 × 3
  2. 2500 ÷ 1,000,000 × 3
  3. 3 ÷ 2500 × 1,000,000
  4. 3 × 2500 ÷ 1,000,000

Answer(s): C



If DPU = 0.022, the RTU is approximately:

  1. 0.022
  2. 0.078
  3. 0.0022
  4. 0.98
  5. 0.098
  6. 0.0098

Answer(s): D



A project activity not on the critical path has required 20% longer than the time originally allocated. The project team should:

  1. inform all concerned that the entire project will be delayed by 20%
  2. inform all concerned that the entire project will be delayed but by less than 20%
  3. study the effect this will have on other activities because the project may still be on schedule

Answer(s): C