You are reviewing the Velocity Chart for your team and notice that they completed more story points than they committed in their last sprint. You are definitely the only person who can add issues to sprints in your project. How did your learn complete more story points than they committed?

  1. The sprint was completed early.
  2. An epic with a story point estimate was completed during the sprint.
  3. Someone increased the story point value on an issue mid-sprint.
  4. A sub-task was in an unmapped status at the start of the sprint.
  5. A new sub-task was created drying the sprint

Answer(s): C

Explanation:

The reason why your team completed more story points than they committed in their last sprint is that someone increased the story point value on an issue mid-sprint. This will increase the total story points completed at the end of the sprint, but not affect the total story points committed at the start of the sprint. Therefore, it will result in a positive scope change. The other reasons mentioned in the question do not explain why your team completed more story points than they committed, as they either do not affect story points at all, or affect both committed and completed story points equally.


Reference:

Viewing the Velocity Chart, Scope change



Gen prioritizes and triages support requests as soon as they come in. She now wants to use drag- and-drop to:
· quickly assign and transition them to in Progress
· instantly associate them with Epics

Which board view will meet these requirements?

  1. Scrum backlog
  2. Kanban board
  3. Kanban backlog
  4. Active sprints

Answer(s): B

Explanation:

A Kanban board is the best option for Gen to prioritize and triage support requests using drag-and- drop. A Kanban board allows Gen to quickly assign issues to herself or other team members by dragging them to the appropriate column. She can also transition issues to In Progress by moving them across the workflow. Additionally, she can instantly associate issues with Epics by dragging them to the Epic panel on the right side of the board. A Kanban board also provides a visual overview of the current status and progress of the support requests.


Reference:

Managing Jira Projects Data Center and Server: Certification Bundle, Configuring projects | Administering Jira applications Data Center and ..., [Working with issues | Jira Software Cloud]



The release manager is requesting a list of all issues included in a particular sprint.
Which report will provide this information?

  1. Control Chart
  2. Release Burndown
  3. Version Report
  4. Sprint Report
  5. Average Age Report

Answer(s): D

Explanation:

A Sprint Report is the best report to provide a list of all issues included in a particular sprint. A Sprint Report shows the scope, status, and completion date of each sprint. It also displays a breakdown of the completed, incomplete, and added issues in the sprint. The release manager can easily view the list of incomplete issues in the Issue Navigator by clicking on the View in Issue Navigator link at the bottom of the report. A Sprint Report also helps to track the team's performance and identify any scope changes during the sprint.


Reference:

Managing Jira Projects Data Center and Server:
Certification Bundle, [Sprint Report | Jira Software Cloud]



Your team failed to meet their last sprint commitment and you want to investigate further. You need an agile report that:
· shows you a list of the incomplete issues in the sprint · allows you to quickly view that list in the Issue Navigator

Which report meets this need?

  1. Burndown Chart
  2. Control Chart
  3. Cumulative Flow Diagram
  4. Sprint Report
  5. Velocity Chart

Answer(s): D

Explanation:

A Sprint Report is also the best report to meet this need. As explained above, a Sprint Report shows a list of the incomplete issues in the sprint and allows you to quickly view that list in the Issue Navigator. A Sprint Report can help you investigate why your team failed to meet their last sprint commitment by showing you how many issues were added or removed during the sprint, how many issues were completed or not completed, and how much work was carried over to the next sprint.


Reference:

Managing Jira Projects Data Center and Server: Certification Bundle, [Sprint Report | Jira Software Cloud]



Page 7 of 19



Post your Comments and Discuss ATLASSIAN ACP-610 exam with other Community members:

Kumar commented on September 01, 2024
Nice qs and
Anonymous
upvote