CompTIA PK0-004 Exam Questions
CompTIA Project+ (Page 27 )

Updated On: 17-Feb-2026

A project manager has been assigned a complex project and does not know all the activities required to complete it. Which of the following if the BEST approach to determine the work packages for the WBS?

  1. Brainstorming
  2. Analogous
  3. Bottom-up
  4. Forward pass

Answer(s): C



Which of the following documents need to be updated as events occur during a project? (Choose two.)

  1. Change request
  2. Risk register
  3. Meeting minutes
  4. Issue log
  5. Status report

Answer(s): C,E



During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?

  1. Change request
  2. Risk mitigation
  3. Change control
  4. Scope creep

Answer(s): D



A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?

  1. Project schedule
  2. Action items
  3. Project charter
  4. Communication plan

Answer(s): A



A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

  1. Add durations.
  2. Add the start and finish dates
  3. Add tasks.
  4. Add resources.

Answer(s): C






Post your Comments and Discuss CompTIA PK0-004 exam dumps with other Community members:

Join the PK0-004 Discussion