Free PK0-004 Exam Braindumps (page: 4)

Page 3 of 182

A stakeholder is unaware of a project’s status.

Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)

  1. Status report
  2. Organizational chart
  3. RACI matrix
  4. Meeting minutes
  5. Communication plan

Answer(s): A,D


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261



There are four parallel paths on a network diagram. The summary duration of each path is below:

A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks

Which of the following tasks are on the critical path?

  1. A, C, G
  2. A, B, F
  3. D, E, H
  4. D, B, F

Answer(s): C


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 175



A project team is comprised of a mix of in-house and virtual team members.
When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?

  1. Composing a project team email with the details of the announcement is the best method. It gives the project manager the opportunity to explain but not be overcome with questions from the team.
  2. Using text messaging to make the announcement is the best method. It allows the project manager to reach the project team members wherever they are located.
  3. Sending a fax is the best method. It gives the project manager the opportunity to explain the announcement and come up with questions and answers the team may have.
  4. Hosting a web conference meeting is the best method. It gives the project manager the opportunity to explain the announcement and answer any questions from the team.

Answer(s): D


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 260



A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?

  1. Backlog
  2. Standup
  3. Kickoff
  4. Retrospective

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306






Post your Comments and Discuss CompTIA PK0-004 exam with other Community members:

PK0-004 Discussions & Posts